Estimated Timeline
2 of 8 stations approved25% complete
Key Milestones
Jun 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2023
Dormant Period
No plan-check activity for ~24 months — applicant-side pause, not city queue time.
Sep 2025
Permit Filed
New construction permit filed with DBI
Sep 2027 – Aug 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 14 mo · Applicant: 0 mo · Dormant: 24 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on April 16, 2026. 2 round(s) of review. Reviewer: Mcelroy Carey.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on April 10, 2026. 2 round(s) of review. Reviewer: Mautner Allegra.
Fire (SFFD)
SF Fire Department
Comments issued on April 24, 2026. 2 round(s) of review. Reviewer: Harshman Kjell.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on March 17, 2026. 2 round(s) of review. Reviewer: Garcia Jobel.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on March 13, 2026. 2 round(s) of review. Reviewer: Chen Bill.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Wong Wesley.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 01, 2025. Reviewer: Dennis Rassendyll.
Public Health (HEALTH)
Dept. of Public Health
Approved September 25, 2025. Reviewer: Huber Joanna.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.