Estimated Timeline
7 of 7 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved January 31, 2024. Reviewer: Page Vincent.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 08, 2024. Reviewer: Choy Clinton.
Building Code (BLDG)
Dept. of Building Inspection
Approved March 26, 2024. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved March 25, 2024. Reviewer: Andrawes Kamal.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved January 29, 2024. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved January 05, 2024. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 18, 2024. Reviewer: Blackshear John.
Key Milestones
Sep 2023
Permit Filed
New construction permit filed with DBI
Sep 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Aug 2024
Permit Issued
Construction can begin