San Francisco / Bernal Heights / 3300 Mission St

3300 Mission St

35-unit 6-story residential project priority processing: new 6-story type iiia over type 1a mixed-use bldg with 35 studio units (100% affordable housing mayor ed 13-01), residential community s...

Reinstated35 UnitsAB 2011 Ministerial$17.0M Est. Cost
Permit Filed
Oct 2023
Active Review Since
Oct 2023
Review Stations
8 of 8
stations approved
Project Status
Reinstated
Estimated Timeline

Permit Issued

July 2024

Permit issued on July 05, 2024. Project moved into construction phase.

Actual permit issuance date from DBI records
8 of 8 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved February 12, 2024. Reviewer: Enchill Charles.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 09, 2024. Reviewer: Devine Theo.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved April 03, 2024. Reviewer: Mcelroy Carey.
Approved
Fire (SFFD)
SF Fire Department
Approved April 03, 2024. Reviewer: Woo Jason.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 13, 2024. Reviewer: Garcia Jobel.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved April 08, 2024. Reviewer: Mautner Allegra.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 23, 2024. Reviewer: Blackshear John.
Approved
Historic Preservation (HIS)
Dept. of Building Inspection
Approved November 17, 2023. Reviewer: Luton Matt.
Approved
Key Milestones
Oct 2023
Permit Filed
New construction permit filed with DBI
Oct 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Permit Issued
Construction can begin
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.