Estimated Timeline
Permit issued — plan check completeJuly 05, 2024
Key Milestones
Oct 2023
Permit Filed
New construction permit filed with DBI
Oct 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 8 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Approved February 12, 2024. Reviewer: Enchill Charles.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 09, 2024. Reviewer: Devine Theo.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 03, 2024. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Approved April 03, 2024. Reviewer: Woo Jason.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 13, 2024. Reviewer: Garcia Jobel.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved April 08, 2024. Reviewer: Mautner Allegra.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 23, 2024. Reviewer: Blackshear John.
Historic Preservation (HIS)
Dept. of Building Inspection
Approved November 17, 2023. Reviewer: Luton Matt.
Construction
Mechanical / MEP
80% completeLatest inspection: Mar 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-08
124CEILING INSPECTIONPASSED
2026-05-19
101START WORK
2026-05-13
135SHEETROCK NAILINGPASSED
2026-05-01
135SHEETROCK NAILINGPASSED
2026-04-29
129SHEAR WALLPASSED
2026-04-24
124CEILING INSPECTIONPASSED
2026-03-16
146MECHANICALPASSED
2026-02-27
124CEILING INSPECTIONPASSED