Estimated Timeline
3 of 8 stations approved37% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on January 24, 2024. 1 round(s) of review. Reviewer: Mcelroy Carey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on February 02, 2024. 1 round(s) of review. Reviewer: Devine Theo.
Fire (SFFD)
SF Fire Department
Comments issued on January 31, 2024. 1 round(s) of review. Reviewer: Lo Jonathan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on January 16, 2024. 1 round(s) of review. Reviewer: Garcia Jobel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 12, 2024. Reviewer: Mautner Allegra.
Planning (CP-ZOC)
SF Planning Department
Approved January 11, 2024. Reviewer: Spycher Dakota.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved March 15, 2024. Reviewer: Szeto David.
Bottleneck Watch: Building Code
Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
Dec 2023
Permit Filed
New construction permit filed with DBI
Dec 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.