San Francisco / Mission / 1500 15Th St

1500 15Th St

179-unit 13-story residential project erect a 13 story,179 dwelling unit with 2 basements mixed use residential with commerical bldg.

Permit Filed — In Plan Check179 UnitsAB 2011 Ministerial$40.8M Est. Cost
Permit Filed
Dec 2023
Active Review Since
Dec 2023
Review Stations
3 of 8
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
3 of 8 stations approved37% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on January 24, 2024. 1 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on February 02, 2024. 1 round(s) of review. Reviewer: Devine Theo.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on January 31, 2024. 1 round(s) of review. Reviewer: Lo Jonathan.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on January 16, 2024. 1 round(s) of review. Reviewer: Garcia Jobel.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 12, 2024. Reviewer: Mautner Allegra.
Approved
Planning (CP-ZOC)
SF Planning Department
Approved January 11, 2024. Reviewer: Spycher Dakota.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved March 15, 2024. Reviewer: Szeto David.
Approved

Bottleneck Watch: Building Code

Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Key Milestones
Dec 2023
Permit Filed
New construction permit filed with DBI
Dec 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.