San Francisco / Mission / 1500 15Th St

1500 15Th St

179-unit 13-story residential project erect a 13 story,179 dwelling unit with 2 basements mixed use residential with commerical bldg.

Dormant179 UnitsAB 2011 MinisterialDBI Valuation $40.8M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 3 mo · Applicant: 0 mo
Permit Filed
Dec 2023
Time in Active Review
3 months
Review Stations
3 of 8
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

September 2026 — March 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
3 of 8 stations approved37% complete
Key Milestones
Dec 2023
Permit Filed
New construction permit filed with DBI
Dec 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Mar 2024
Currently Dormant
No plan-check activity for 895 days so far — applicant-side pause, not city queue time.
Sep 2026 – Mar 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 3 mo · Applicant: 0 mo · Dormant: 29 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on January 24, 2024. 1 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on February 02, 2024. 1 round(s) of review. Reviewer: Devine Theo.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on January 31, 2024. 1 round(s) of review. Reviewer: Lo Jonathan.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on January 16, 2024. 1 round(s) of review. Reviewer: Garcia Jobel.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 12, 2024. Reviewer: Mautner Allegra.
Approved
Planning (CP-ZOC)
SF Planning Department
Approved January 11, 2024. Reviewer: Spycher Dakota.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved March 15, 2024. Reviewer: Szeto David.
Approved

Bottleneck Watch: Building Code

Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.