San Francisco / Presidio Heights / 1945 Lyon St

1945 Lyon St

6-unit residential project entitled — awaiting building permit

Entitled — No Permit Yet6 UnitsPlanning Entitlement
Entitlement
Mar 2026
Plan Check
Awaiting Issuance
Construction
Complete
Planning Filed
Oct 2024
Units Proposed
6
net new
Status
Entitled — No Permit Yet
Closed - Approval Ltr Issued
Stage
Entitlement
pre-building-permit
Entitlement Tracking

Entitled — Awaiting Building Permit

Planning entitlement approved. The building permit has not yet been filed with DBI. Full plan-check tracking (station-by-station status, timeline estimate, construction) begins when the DBI permit appears.

SF Planning entitlement record
Plans & Renderings
Key Milestones
Oct 2024
Planning Application Filed
Entitlement application opened with SF Planning.
Mar 2026
Entitlement Approved
Planning approval granted. Next step: building permit filing with DBI.
Building Permit Filing
DBI permit not yet filed. Full tracking begins when it appears.
Data sources: Entitlement-stage record from the SF Planning Department Records - Projects dataset (Socrata qvu5-m3a2). Full plan-check tracking begins once a DBI building permit is filed. See DataSF Building Permit Addenda with Routing.