Estimated Timeline
Permit issued — plan check completeJuly 12, 2024
Key Milestones
Jan 2024
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2024
Permit Filed
New construction permit filed with DBI
Mar 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 6 mo · Applicant: 0 mo
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved June 26, 2024. Reviewer: Dennis Rassendyll.
Building Code (BLDG)
Dept. of Building Inspection
Approved June 21, 2024. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Approved June 11, 2024. Reviewer: Andrawes Kamal.
Public Health (HEALTH)
Dept. of Public Health
Approved May 02, 2024. Reviewer: Chen Bill.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 10, 2024. Reviewer: Garcia Jobel.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 03, 2024. Reviewer: Bryan Ong.
Planning (CP-ZOC)
SF Planning Department
Approved March 11, 2024. Reviewer: Sucre Richard.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 27, 2024. Reviewer: Blackshear John.
Construction
Mechanical / MEP
80% completeLatest inspection: Jul 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-21
111SITE VERIFICATIONPASSED
2026-08-20
111SITE VERIFICATIONPASSED
2026-08-19
111SITE VERIFICATIONPASSED
2026-08-04
122REINFORCING STEEL
2026-07-29
127INSULATIONPASSED
2026-07-24
148OTHER
2026-07-22
132FLUES/VENTS/DUCTSPASSED
2026-07-22
132FLUES/VENTS/DUCTS