Estimated Timeline
8 of 8 stations approved100% complete
Plan Check Status
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 06, 2025. Reviewer: Kwong John.
Fire (SFFD)
SF Fire Department
Approved February 04, 2025. Reviewer: Andrawes Kamal.
Building Code (BLDG)
Dept. of Building Inspection
Approved January 14, 2025. Reviewer: Soenksen Richard.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 02, 2024. Reviewer: Imson Grace.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved November 05, 2024. Reviewer: Bryan Ong.
Planning (CP-ZOC)
SF Planning Department
Approved October 29, 2024. Reviewer: Mau Elizabeth.
Public Health (HEALTH)
Dept. of Public Health
Approved October 18, 2024. Reviewer: Chen Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved February 07, 2025. Reviewer: Blackshear John.
Key Milestones
Mar 2024
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2024
Permit Filed
New construction permit filed with DBI
Oct 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Feb 2025
Permit Issued
Construction can begin