San Francisco / Treasure Island / 150 04Th Ti St

150 04Th Ti St

120-unit 6-story residential project mayoral ed 13-01/17-02: erect new 6-story bldg

Permit Issued — Under Construction120 UnitsAB 2011 Ministerial$40.0M Est. Cost
Permit Filed
Oct 2024
Active Review Since
Mar 2024
Review Stations
8 of 8
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

February 2025

Permit issued on February 14, 2025. Project moved into construction phase.

Actual permit issuance date from DBI records
8 of 8 stations approved100% complete
Plan Check Status
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 06, 2025. Reviewer: Kwong John.
Approved
Fire (SFFD)
SF Fire Department
Approved February 04, 2025. Reviewer: Andrawes Kamal.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved January 14, 2025. Reviewer: Soenksen Richard.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 02, 2024. Reviewer: Imson Grace.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved November 05, 2024. Reviewer: Bryan Ong.
Approved
Planning (CP-ZOC)
SF Planning Department
Approved October 29, 2024. Reviewer: Mau Elizabeth.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved October 18, 2024. Reviewer: Chen Bill.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved February 07, 2025. Reviewer: Blackshear John.
Approved
Key Milestones
Mar 2024
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2024
Permit Filed
New construction permit filed with DBI
Oct 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Feb 2025
Permit Issued
Construction can begin