San Francisco / Nob Hill / 1123 Sutter St

1123 Sutter St

201-unit 22-story residential project this permit# 202411215452 is only for the 201 market rate housing units and for the mixed occupancies: r-2,a-3,m,e

Permit Issued — Under Construction201 UnitsAB 2011 Ministerial$80.0M Est. Cost
Permit Filed
Jan 2025
Active Review Since
Nov 2024
Review Stations
11 of 11
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

October 2025

Permit issued on October 16, 2025. Project moved into construction phase.

Actual permit issuance date from DBI records
11 of 11 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved October 09, 2025. Reviewer: Spycher Dakota.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved June 25, 2025. Reviewer: Liu Stephen.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved June 23, 2025. Reviewer: Chung Diana.
Approved
Fire (SFFD)
SF Fire Department
Approved June 21, 2025. Reviewer: Woo Jason.
Approved
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Approved June 20, 2025. Reviewer: Jacobo Marco.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved June 18, 2025. Reviewer: Bendezu Sebastian.
Approved
Mechanical (MECH)
Dept. of Building Inspection
Approved June 18, 2025. Reviewer: Tan (Peter) Jia Jian.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved June 11, 2025. Reviewer: Choy Clinton.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved January 06, 2025. Reviewer: Hoang Tina.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved July 02, 2025. Reviewer: Blackshear John.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved January 02, 2025. Reviewer: Obana Doug.
Approved
Key Milestones
Nov 2024
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2025
Permit Filed
New construction permit filed with DBI
Oct 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2025
Permit Issued
Construction can begin
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.