Estimated Timeline
Permit issued — plan check completeNovember 07, 2025
Key Milestones
Dec 2024
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2025
Permit Filed
New construction permit filed with DBI
Aug 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2025
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 10 mo · Applicant: 2 mo
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved October 23, 2025. Reviewer: Chen Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 02, 2025. Reviewer: Dennis Rassendyll.
Building Code (BLDG)
Dept. of Building Inspection
Approved September 09, 2025. Reviewer: Bendezu Sebastian.
Fire (SFFD)
SF Fire Department
Approved September 08, 2025. Reviewer: Andrawes Kamal.
Planning (CP-ZOC)
SF Planning Department
Approved August 18, 2025. Reviewer: Salgado Rebecca.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved June 20, 2025. Reviewer: Wong Laura.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 24, 2025. Reviewer: Blackshear John.
Public Health (HEALTH)
Dept. of Public Health
Approved February 12, 2025. Reviewer: Veloso Rochelle.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved February 12, 2025. Reviewer: Chan Thomas.
Construction
Foundation / Pour
25% completeLatest inspection: Aug 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-19
123OK TO POURPASSED
2026-08-18
123OK TO POURPASSED
2026-08-06
123OK TO POURPASSED
2026-07-22
123OK TO POURPASSED
2026-06-18
111SITE VERIFICATIONPASSED
2026-06-12
111SITE VERIFICATIONPASSED
2026-05-28
801INSP QUALITY CONTROL FIELDPASSED
2026-05-28
801INSP QUALITY CONTROL FIELD