San Francisco / All Projects / 222 Capp St

222 Capp St

70-unit residential project entitled — awaiting building permit

Entitled — No Permit Yet70 UnitsPlanning Entitlement
Entitlement
Jun 2026
Plan Check
Awaiting Issuance
Construction
Complete
Planning Filed
Nov 2025
Units Proposed
70
net new
Status
Entitled — No Permit Yet
Closed - Approval Ltr Issued
Stage
Entitlement
pre-building-permit
Entitlement Tracking

Entitled — Awaiting Building Permit

Planning entitlement approved. The building permit has not yet been filed with DBI. Full plan-check tracking (station-by-station status, timeline estimate, construction) begins when the DBI permit appears.

SF Planning entitlement record
Key Milestones
Nov 2025
Planning Application Filed
Entitlement application opened with SF Planning.
Jun 2026
Entitlement Approved
Planning approval granted. Next step: building permit filing with DBI.
Building Permit Filing
DBI permit not yet filed. Full tracking begins when it appears.
Data sources: Entitlement-stage record from the SF Planning Department Records - Projects dataset (Socrata qvu5-m3a2). Full plan-check tracking begins once a DBI building permit is filed. See DataSF Building Permit Addenda with Routing.