San Francisco / Pacific Heights / 2395 Sacramento St

2395 Sacramento St

10-unit 8-story residential project to erect a 8 stories,10 dwellings with 1 basement bldg, type 1-b.

Blocked in Review10 UnitsAB 2011 MinisterialDBI Valuation $5.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Blocked in review. City desk: 19 mo · Applicant: 0 mo
Permit Filed
Mar 2025
Time in Active Review
19 months
Review Stations
6 of 7
stations approved
Project Status
Blocked in Review
Estimated Timeline

Permit Issuance Estimate

September 2026 — May 2028

Timeline driven by 1 station cycling repeatedly on comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 1 unapproved station
6 of 7 stations approved85% complete
Key Milestones
Jan 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2025
Permit Filed
New construction permit filed with DBI
Sep 2026 – May 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 19 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Cycling through 5 rounds of comments without clearing. Most recent review: July 30, 2026. Reviewer: Taylor Michelle.
Blocked
Fire (SFFD)
SF Fire Department
Approved February 09, 2026. Reviewer: Lo Jonathan.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved July 30, 2025. Reviewer: Soenksen Richard.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved July 15, 2025. Reviewer: Tjalsma Jason.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 23, 2025. Reviewer: Dennis Rassendyll.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 24, 2025. Reviewer: Imson Grace.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 01, 2026. Reviewer: Blackshear John.
Approved

Bottleneck Watch: Planning

Planning has been the single biggest drag on this project's timeline. The reviewer has issued comments across 5 rounds of review without clearing the station. Until the underlying issues are resolved or escalated, no amount of revision cycles on other stations will unblock permit issuance.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.