Estimated Timeline
6 of 7 stations approved85% complete
Key Milestones
Jan 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2025
Permit Filed
New construction permit filed with DBI
Sep 2026 – May 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 19 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Cycling through 5 rounds of comments without clearing. Most recent review: July 30, 2026. Reviewer: Taylor Michelle.
Fire (SFFD)
SF Fire Department
Approved February 09, 2026. Reviewer: Lo Jonathan.
Building Code (BLDG)
Dept. of Building Inspection
Approved July 30, 2025. Reviewer: Soenksen Richard.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved July 15, 2025. Reviewer: Tjalsma Jason.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 23, 2025. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 24, 2025. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 01, 2026. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning has been the single biggest drag on this project's timeline. The reviewer has issued comments across 5 rounds of review without clearing the station. Until the underlying issues are resolved or escalated, no amount of revision cycles on other stations will unblock permit issuance.