Estimated Timeline
9 of 9 stations approved100% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Approved August 15, 2025. Reviewer: Bendezu Sebastian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 30, 2025. Reviewer: Imson Grace.
Fire (SFFD)
SF Fire Department
Approved July 29, 2025. Reviewer: Woo Jason.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 25, 2025. Reviewer: Kwong John.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved June 20, 2025. Reviewer: Hu Claire.
Planning (CP-ZOC)
SF Planning Department
Approved May 07, 2025. Reviewer: Horn Jeffrey.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved April 30, 2025. Reviewer: Nawbary Susan.
Public Health (HEALTH)
Dept. of Public Health
Approved April 15, 2025. Reviewer: Hoang Tina.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 21, 2025. Reviewer: Luu Sarah.
Key Milestones
Mar 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2025
Permit Filed
New construction permit filed with DBI
May 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2025
Permit Issued
Construction can begin