Estimated Timeline
11 of 11 stations approved100% complete
Plan Check Status
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 14, 2026. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved December 30, 2025. Reviewer: Ghale Raymon Louis.
Building Code (BLDG)
Dept. of Building Inspection
Approved December 02, 2025. Reviewer: Ospital Joseph.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved November 26, 2025. Reviewer: Liu Stephen.
Planning (CP-ZOC)
SF Planning Department
Approved November 12, 2025. Reviewer: Laush Maggie.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved November 06, 2025. Reviewer: Mautner Allegra.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Approved November 06, 2025. Reviewer: Jaser Sam.
Mechanical (MECH)
Dept. of Building Inspection
Approved September 15, 2025. Reviewer: Tan (Peter) Jia Jian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved June 09, 2025. Reviewer: Imson Grace.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved June 04, 2025. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved January 15, 2026. Reviewer: Blackshear John.
Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
May 2025
Permit Filed
New construction permit filed with DBI
Nov 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jan 2026
Permit Issued
Construction can begin