San Francisco / Mission / 1721 15Th St

1721 15Th St

48-unit 6-story residential project front bldg: construction of a 6 story residential type iii-a over i-a building with 48 residential dwelling units.

Permit Issued48 UnitsAB 2011 MinisterialDBI Valuation $6.9M
Entitlement
Plan Check
Jan 2026
Awaiting Issuance
Jan 2026
Post-Issuance Addenda
Construction
Complete
Construction: Shear Wall / Structural (45%). Last inspection: Jul 2026.
Permit Filed
May 2025
Time in Active Review
9 months
Permit Issued
Jan 2026
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

January 2026

Permit issued on January 26, 2026. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJanuary 26, 2026
Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
May 2025
Permit Filed
New construction permit filed with DBI
Nov 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jan 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 14, 2026. Reviewer: Dennis Rassendyll.
Approved
Fire (SFFD)
SF Fire Department
Approved December 30, 2025. Reviewer: Ghale Raymon Louis.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved December 02, 2025. Reviewer: Ospital Joseph.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved November 26, 2025. Reviewer: Liu Stephen.
Approved
Planning (CP-ZOC)
SF Planning Department
Approved November 12, 2025. Reviewer: Laush Maggie.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved November 06, 2025. Reviewer: Mautner Allegra.
Approved
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Approved November 06, 2025. Reviewer: Jaser Sam.
Approved
Mechanical (MECH)
Dept. of Building Inspection
Approved September 15, 2025. Reviewer: Tan (Peter) Jia Jian.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved June 09, 2025. Reviewer: Imson Grace.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved June 04, 2025. Reviewer: Casey Ryan.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved January 15, 2026. Reviewer: Blackshear John.
Approved
Construction
Shear Wall / Structural
45% completeLatest inspection: Jul 2026
Construction startedMar 2026
Total inspections13
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-28
129SHEAR WALLPASSED
2026-07-20
122REINFORCING STEELPASSED
2026-06-26
122REINFORCING STEEL
2026-06-26
122REINFORCING STEELPASSED
2026-06-02
122REINFORCING STEEL
2026-06-01
122REINFORCING STEELPASSED
2026-05-15
801INSP QUALITY CONTROL FIELDPASSED
2026-05-11
122REINFORCING STEELPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.