Estimated Timeline
Permit issued — plan check completeJuly 01, 2026
Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2025
Permit Filed
New construction permit filed with DBI
May 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Approved May 27, 2026. Reviewer: Dacey John.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 26, 2026. Reviewer: Mautner Allegra.
Building Code (BLDG)
Dept. of Building Inspection
Approved May 06, 2026. Reviewer: Diaz Jonathan.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 17, 2026. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 11, 2025. Reviewer: Arriola Laura.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved June 03, 2025. Reviewer: Hoang Tina.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 02, 2026. Reviewer: Blackshear John.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved June 02, 2025. Reviewer: Louie Timothy.
Post-Issuance Addenda
Addendum #2In Review
4 of 8 stations approved· last activity 2026-08
Addendum #3In Review
0 of 2 stations approved· last activity 2026-08
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.