Estimated Timeline
Permit issued — plan check completeSeptember 02, 2025
Key Milestones
Jun 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2025
Permit Filed
New construction permit filed with DBI
Jul 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2025
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 3 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Approved August 20, 2025. Reviewer: Finnegan John.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 24, 2025. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved July 23, 2025. Reviewer: Mautner Allegra.
Planning (CP-ZOC)
SF Planning Department
Approved July 10, 2025. Reviewer: Pantoja Gabriela.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 09, 2025. Reviewer: Imson Grace.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved June 12, 2025. Reviewer: Hoang Tina.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 28, 2025. Reviewer: Blackshear John.
Construction
Foundation / Rebar
20% completeLatest inspection: Aug 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-26
122REINFORCING STEELPASSED
2026-08-18
122REINFORCING STEELPASSED
2026-08-13
122REINFORCING STEELPASSED
2026-08-13
122REINFORCING STEEL
2026-08-10
122REINFORCING STEEL
2026-08-10
122REINFORCING STEELPASSED
2026-07-28
122REINFORCING STEELPASSED
2026-07-23
122REINFORCING STEELPASSED