Estimated Timeline
Permit issued — plan check completeJuly 01, 2026
Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2025
Permit Filed
New construction permit filed with DBI
Apr 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved April 30, 2026. Reviewer: Kwong John.
Fire (SFFD)
SF Fire Department
Approved April 14, 2026. Reviewer: Andrawes Kamal.
Planning (CP-ZOC)
SF Planning Department
Approved April 09, 2026. Reviewer: Mau Elizabeth.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 08, 2026. Reviewer: Cioni Joseph.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved January 05, 2026. Reviewer: Chen Bill.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 11, 2025. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 29, 2025. Reviewer: Arriola Laura.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved May 05, 2026. Reviewer: Blackshear John.
Historic Preservation (HIS)
Dept. of Building Inspection
Approved June 24, 2025. Reviewer: Lawrie James.
Post-Issuance Addenda
Addendum #1In Review
2 of 7 stations approved· last activity 2026-08
Addendum #2In Review
2 of 9 stations approved· last activity 2026-08
Addendum #3In Review
4 of 12 stations approved· last activity 2026-08
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.