Estimated Timeline
6 of 9 stations approved66% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Comments issued on December 05, 2025. 2 round(s) of review. Reviewer: Mau Elizabeth.
Fire (SFFD)
SF Fire Department
Comments issued on December 23, 2025. 2 round(s) of review. Reviewer: Andrawes Kamal.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 08, 2026. Reviewer: Cioni Joseph.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved January 05, 2026. Reviewer: Chen Bill.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 11, 2025. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 29, 2025. Reviewer: Arriola Laura.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 22, 2025. Reviewer: Kwong John.
Historic Preservation (HIS)
Dept. of Building Inspection
Approved June 24, 2025. Reviewer: Lawrie James.
Bottleneck Watch: Fire
Fire currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2025
Permit Filed
New construction permit filed with DBI
May 2026 – Jun 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.