San Francisco / Treasure Island / 401 California Av

401 California Av

150-unit 6-story residential project to erect 6 stories, no basement, type i-a & ii-a, 150 units residential units with child development center (warmshell), (r-2, b,a-3,s-1,s-2,i-4)

Permit Filed — In Plan Check150 UnitsAB 2011 Ministerial$112.4M Est. Cost
Permit Filed
Jul 2025
Active Review Since
May 2025
Review Stations
6 of 9
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

May 2026 — June 2027

Timeline driven by 2 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 3 unapproved stations
6 of 9 stations approved66% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Comments issued on December 05, 2025. 2 round(s) of review. Reviewer: Mau Elizabeth.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on December 23, 2025. 2 round(s) of review. Reviewer: Andrawes Kamal.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Building Code (BLDG)
Dept. of Building Inspection
Approved April 08, 2026. Reviewer: Cioni Joseph.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved January 05, 2026. Reviewer: Chen Bill.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 11, 2025. Reviewer: Bryan Ong.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 29, 2025. Reviewer: Arriola Laura.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 22, 2025. Reviewer: Kwong John.
Approved
Historic Preservation (HIS)
Dept. of Building Inspection
Approved June 24, 2025. Reviewer: Lawrie James.
Approved

Bottleneck Watch: Fire

Fire currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Key Milestones
May 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2025
Permit Filed
New construction permit filed with DBI
May 2026 – Jun 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.