Estimated Timeline
8 of 8 stations approved100% complete
Plan Check Status
Fire (SFFD)
SF Fire Department
Approved December 04, 2025. Reviewer: Andrawes Kamal.
Building Code (BLDG)
Dept. of Building Inspection
Approved November 13, 2025. Reviewer: Soenksen Richard.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved November 13, 2025. Reviewer: Imson Grace.
Planning (CP-ZOC)
SF Planning Department
Approved September 08, 2025. Reviewer: Mau Elizabeth.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved August 28, 2025. Reviewer: Bryan Ong.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved July 18, 2025. Reviewer: Chen Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 15, 2025. Reviewer: Kwong John.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved December 05, 2025. Reviewer: Blackshear John.
Key Milestones
Jul 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2025
Permit Filed
New construction permit filed with DBI
Sep 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jan 2026
Permit Issued
Construction can begin