Estimated Timeline
4 of 7 stations approved57% complete
Key Milestones
Nov 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2025
Permit Filed
New construction permit filed with DBI
Jan 2026
Currently Dormant
No plan-check activity for 226 days so far — applicant-side pause, not city queue time.
Sep 2026 – Nov 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 2 mo · Applicant: 0 mo · Dormant: 7 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on January 13, 2026. 1 round(s) of review. Reviewer: Bendezu Sebastian.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on December 24, 2025. 1 round(s) of review. Reviewer: Bryan Ong.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Approved December 15, 2025. Reviewer: Berona Marcus.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved December 11, 2025. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 04, 2025. Reviewer: Garcia Jobel.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved December 01, 2025. Reviewer: Chen Bill.
Bottleneck Watch: Building Code
Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.