San Francisco / Western Addition / 700 Golden Gate Av

700 Golden Gate Av

96-unit 8-story residential project erect a phase 2, type 1b, 8-story mixed use building with 96 affordable residential units and parking spaces

Permit Filed — In Plan Check96 UnitsAB 2011 Ministerial$39.2M Est. Cost
Permit Filed
Nov 2025
Active Review Since
Nov 2025
Review Stations
4 of 7
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

May 2026 — October 2026

Timeline driven by 2 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 3 unapproved stations
4 of 7 stations approved57% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on January 13, 2026. 1 round(s) of review. Reviewer: Bendezu Sebastian.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on December 24, 2025. 1 round(s) of review. Reviewer: Bryan Ong.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Fire (SFFD)
SF Fire Department
Approved December 15, 2025. Reviewer: Berona Marcus.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved December 11, 2025. Reviewer: Dennis Rassendyll.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 04, 2025. Reviewer: Garcia Jobel.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved December 01, 2025. Reviewer: Chen Bill.
Approved

Bottleneck Watch: Building Code

Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Key Milestones
Nov 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2025
Permit Filed
New construction permit filed with DBI
May 2026 – Oct 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.