Estimated Timeline
0 of 9 stations approved0% complete
Key Milestones
Nov 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2027 – Dec 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 8 mo
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Not yet routed to this station.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Not yet routed to this station.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Planning
Planning has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.