San Francisco / South of Market / 360 05Th St

360 05Th St

272-unit 21-story residential project erect type 1a over 4a 21-story 272 unit residential/commerical building.

Permit Filed — In Plan Check272 UnitsAB 2011 Ministerial$40.0M Est. Cost
Permit Filed
Feb 2026
Active Review Since
Nov 2025
Review Stations
3 of 9
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

September 2026 — January 2028

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 6 unapproved stations
3 of 9 stations approved33% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on March 24, 2026. 1 round(s) of review. Reviewer: Soenksen Richard.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on March 19, 2026. 1 round(s) of review. Reviewer: Bryan Ong.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on March 17, 2026. 2 round(s) of review. Reviewer: Ghale Raymon Louis.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on March 09, 2026. 1 round(s) of review. Reviewer: Imson Grace.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Giacomucci Monica.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 19, 2026. Reviewer: Dennis Rassendyll.
Approved
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Louie Timothy.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Casey Ryan.
Approved

Bottleneck Watch: Fire

Fire currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Key Milestones
Nov 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2026
Permit Filed
New construction permit filed with DBI
Sep 2026 – Jan 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.