San Francisco / Outer Richmond / 5400 Geary Bl

5400 Geary Bl

83-unit 8-story residential project erect new type 1a 8-stories mix-use building: 83 residental units w/ commercial.

In Plan Check83 UnitsAB 2011 MinisterialDBI Valuation $43.0M
Entitlement
Opened May 2026
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 9 months in active review. City desk: 8 mo · Applicant: 0 mo
Permit Filed
Mar 2026
Time in Active Review
9 months
Review Stations
2 of 7
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

September 2026 — June 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
2 of 7 stations approved28% complete
The Story So Far

The vacant Alexandria Theater at 5400 Geary Bl has resisted redevelopment since closing in 2004. The Chronicle reported that an earlier concept approved in 2013 combined a theater, restaurant, commercial space and housing. A later proposal featured offices, learning space and an indoor pool. Neither moved forward.

TimeSpace Group completed 43 residences on the former adjacent parking lot in 2018, according to the Chronicle, but left the theater undeveloped. TimeSpace Alexandria LLC and the city’s Office of Economic and Workforce Development signed a memorandum of understanding on March 7, 2024, to continue negotiating the property’s future.

On May 16, 2025, San Francisco enacted the Alexandria Theater Special Use District, allowing a density bonus and changes to zoning controls for housing at the site. The Chronicle reported that housing advocates split over the approach. Grow the Richmond supported adding homes, while critics questioned parcel-specific zoning and the cost of historic preservation. The publication also reported uncertainty around financing and construction in a difficult building market.

Preliminary plans reported on November 28, 2025, called for removing most of the deteriorating theater while preserving or reconstructing its marquee, blade sign, chandelier, Art Deco murals and bas-relief panels. SFYIMBY reported on March 16, 2026, that new building permits had been filed, though construction cost and timing remained undisclosed.

The August 2026 dossier now describes an 8-story, 83-unit project using the AB 2011 ministerial pathway. The mix includes 14 one-bedroom, 51 two-bedroom and 18 three-bedroom homes, with 10 affordable units. The permit remains in review with planner Manushi Mathur. A feasibility scenario for 74 units estimates a 5.1 yield on cost against a 6.5 requirement, a gap of 141 basis points below the target. The Outer Richmond pipeline contains 21 projects totaling 812 units.

Sources: San Francisco YIMBY (2026-03) · San Francisco YIMBY (2025-11) · San Francisco Board of Supervisors (2025-05) · San Francisco Chronicle (2025-05) · Richmond Review/Sunset Beacon (2024-03)
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2026
Permit Filed
New construction permit filed with DBI
Sep 2026 – Jun 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on May 11, 2026. 1 round(s) of review. Reviewer: Zee Alan.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Comments issued on June 08, 2026. 2 round(s) of review. Reviewer: Sucre Richard.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on April 23, 2026. 1 round(s) of review. Reviewer: Sullivan Cadhan.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on June 16, 2026. 1 round(s) of review. Reviewer: Weiss-Ishai Sagiv.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 07, 2026. Reviewer: Imson Grace.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 17, 2026. Reviewer: Dennis Rassendyll.
Approved

Bottleneck Watch: Planning

Planning currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.