Estimated Timeline
2 of 7 stations approved28% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved April 07, 2026. Reviewer: Imson Grace.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 17, 2026. Reviewer: Dennis Rassendyll.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2026
Permit Filed
New construction permit filed with DBI
Jul 2026 – Jun 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.