San Francisco / Presidio Heights / 519 Walnut St

519 Walnut St

61-unit 5-story residential project plaza building-b wing: priority mayor's ed 17-02 - erect a type 1b, 5-story, 1 bsmnt, mixed-use bldg with 61 residential units, bsmnt parking, and commercial...

In Plan Check61 UnitsAB 2011 MinisterialDBI Valuation $47.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 9 months in active review. City desk: 8 mo · Applicant: 1 mo
Permit Filed
Feb 2026
Time in Active Review
9 months
Review Stations
2 of 7
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

September 2026 — May 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
2 of 7 stations approved28% complete
The Story So Far

The 519 Walnut St proposal would bring a 5-story, 61-unit building to the former UCSF Laurel Heights campus in Presidio Heights. The site remains occupied by a vacant mid-century office complex and extensive parking awaiting redevelopment.

The project forms part of Presidio Highlands, a larger redevelopment planned by Prado Group. The master plan calls for 744 apartments, approximately 38,100 square feet of retail, a 175-seat child-care facility, five acres of open space, and parking for as many as 820 cars and 839 bicycles, according to SFYIMBY.

Prado Group and SKS Partners won unanimous Board of Supervisors approval for the 744-home redevelopment on November 13, 2019, after project opponents appealed the plan. Opposition also included a campaign against removing hundreds of mature trees. In January 2020, the Laurel Heights Improvement Association sued San Francisco, alleging that the approval violated the California Environmental Quality Act.

The city advanced an infrastructure-financing district in January 2026. The Chronicle reported that future property-tax growth could help fund utilities, parks, affordable housing, and other upfront project costs. Prado Group said the first three buildings were expected to begin construction in late 2026 and collectively add 152 homes, retail, and public open space.

The 519 Walnut St permit was filed in February 2026 under the AB 2011 ministerial pathway. The August 2026 dossier update shows the application remains in review. The parcel has 7 prior permits and no dead planning records. A feasibility model tests 60 units and estimates a 4.2 yield on cost against a 6.5 requirement, leaving the proposal 228 basis points below the modeled threshold. The broader neighborhood pipeline contains 27 projects and 740 units.

Sources: San Francisco YIMBY (2026-02) · San Francisco Chronicle (2026-01) · San Francisco Business Times (2019-11) · San Francisco Chronicle (2020-01) · ABC7 San Francisco (2019-11)
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2026
Permit Filed
New construction permit filed with DBI
Sep 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on June 11, 2026. 2 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Comments issued on August 25, 2026. 3 round(s) of review. Reviewer: Horn Jeffrey.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on May 28, 2026. 2 round(s) of review. Reviewer: Bryan Ong.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on August 14, 2026. 4 round(s) of review. Reviewer: Chung Diana.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 24, 2026. Reviewer: Chan Desmond.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved February 20, 2026. Reviewer: Chen Bill.
Approved

Bottleneck Watch: Planning

Planning currently has open comments after 3 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.