San Francisco / Presidio Heights / 528 Laurel St

528 Laurel St

62-unit 5-story residential project plaza building-a wing: priority mayor's ed 17-02 - erect a type 1b, 5-story, 1 bsmnt, mixed-use bldg with 62 residential units, bsmnt parking, and commercial...

In Plan Check62 UnitsAB 2011 MinisterialDBI Valuation $26.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 9 months in active review. City desk: 8 mo · Applicant: 1 mo
Permit Filed
Feb 2026
Time in Active Review
9 months
Review Stations
2 of 7
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

September 2026 — May 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 5 unapproved stations
2 of 7 stations approved28% complete
The Story So Far

The 528 Laurel St proposal would add 62 homes in a 5-story building at the former UCSF Laurel Heights campus in Presidio Heights. The site remains vacant, with a midcentury office building and extensive surface parking. The project is pursuing AB 2011 ministerial approval and remains in review following its February 2026 filing.

The proposal forms part of the broader Presidio Highlands redevelopment. In December 2014, SKS Partners and Prado Group signed a 99-year ground lease with UCSF for the 10.3-acre campus. Opponents later secured historic designation for the main building, the San Francisco Business Times reported in 2018. Prado Group and SKS Partners then won unanimous Board of Supervisors approval for a 744-home master development in 2019 after defeating appeals.

Laurel Heights residents sued the city in 2020 over the redevelopment’s environmental review, according to the San Francisco Standard. The parties subsequently settled the litigation. UCSF closed the campus in June 2023 after occupying it since the late 1980s. The office building had housed about 1,200 employees, and the property later served as a pandemic vaccination and testing center.

The current development phase advanced in February 2026, when SF YIMBY reported permit filings for the first three Presidio Highlands buildings, representing 152 homes. The publication identified Prado Group as the developer. In January 2026, the Chronicle reported that construction was expected to begin in late 2026.

The August 2026 dossier update shows the 528 Laurel St permit still under review. The parcel has 7 prior permits and no dead planning records. Presidio Heights has 27 pipeline projects totaling 739 homes. The tracker’s feasibility model finds the project eligible but not financially feasible, with a 5 yield on cost against a 6.5 requirement and a 147-basis-point shortfall.

Sources: San Francisco Chronicle (2026-01) · San Francisco YIMBY (2026-02) · San Francisco Standard (2024-04) · San Francisco Business Times (2019-11) · San Francisco Business Times (2018-11) · UC San Francisco (2023-06) · San Francisco Business Times (2014-12)
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2026
Permit Filed
New construction permit filed with DBI
Sep 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on June 11, 2026. 2 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Comments issued on August 25, 2026. 3 round(s) of review. Reviewer: Horn Jeffrey.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on May 28, 2026. 3 round(s) of review. Reviewer: Bryan Ong.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on August 14, 2026. 4 round(s) of review. Reviewer: Chung Diana.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved February 20, 2026. Reviewer: Chen Bill.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 19, 2026. Reviewer: Chan Desmond.
Approved

Bottleneck Watch: Planning

Planning currently has open comments after 3 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.