San Francisco / Presidio Heights / 538 Laurel St

538 Laurel St

31-unit 4-story residential project mayfair building: priority mayor's ed 17-02 - erect a type 1b, 4-story over 1 basement mixed-use building with 31 residential dwelling units.

In Plan Check31 UnitsAB 2011 MinisterialDBI Valuation $15.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 9 months in active review. City desk: 8 mo · Applicant: 1 mo
Permit Filed
Feb 2026
Time in Active Review
9 months
Review Stations
3 of 7
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

May 2027 — April 2029

Timeline driven by 3 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 4 unapproved stations
3 of 7 stations approved42% complete
The Story So Far

The proposal at 538 Laurel St would add 31 units in a 4-story building under the AB 2011 ministerial pathway. The site forms part of the former UCSF Laurel Heights office campus in Presidio Heights, which the Chronicle described in January 2026 as vacant.

The broader redevelopment dates to December 2014, when SKS Partners and Prado Group signed a 99-year ground lease with UCSF for the 10.3-acre campus, according to the San Francisco Business Times. Opponents later secured historic designation for the central modernist building in November 2018. Prado Group and SKS Partners won unanimous Board of Supervisors approval for the master development in November 2019 after defeating project appeals.

The Laurel Heights Improvement Association sued San Francisco in January 2020, alleging inadequate environmental review and significant neighborhood impacts. The Chronicle reported in September 2024 that the lawsuit ended in a settlement. In October 2024, city staff recommended changes to support infrastructure-district financing, extend the development agreement and revise affordable-housing requirements. SFYIMBY reported an estimated construction cost of at least $450 million.

The project moved toward construction in 2026. The Chronicle reported in January 2026 that Prado Group expected to begin work in late 2026 on the first three buildings. SFYIMBY reported in February 2026 that new-building permits had been filed for 538 Laurel St and two companion buildings. BAR Architects & Interiors designed the metal-panel and dark-wood-shingle exterior.

The 538 Laurel St permit remains in review as of August 2026. The dossier identifies 7 prior permits and no dead planning records at the parcel. The feasibility model finds the project eligible but estimates a 4.4 yield on cost against a required 6.5, leaving it 207 basis points below the threshold.

Sources: San Francisco Chronicle (2026-01) · San Francisco YIMBY (2026-02) · San Francisco YIMBY (2024-10) · San Francisco Chronicle (2024-09) · San Francisco Chronicle (2020-01) · San Francisco Business Times (2019-11) · San Francisco Business Times (2018-11) · San Francisco Business Times (2014-12)
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2026
Permit Filed
New construction permit filed with DBI
May 2027 – Apr 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 8 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on June 11, 2026. 2 round(s) of review. Reviewer: Mcelroy Carey.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Comments issued on August 25, 2026. 3 round(s) of review. Reviewer: Horn Jeffrey.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on August 13, 2026. 4 round(s) of review. Reviewer: Chung Diana.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 28, 2026. Reviewer: Bryan Ong.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved February 20, 2026. Reviewer: Chen Bill.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 19, 2026. Reviewer: Kwong John.
Approved

Bottleneck Watch: Planning

Planning currently has open comments after 3 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.