Estimated Timeline
Permit issued — plan check completeJune 17, 2026
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2025
Permit Filed
New construction permit filed with DBI
Jan 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jun 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 1 mo
Building Code (BLDG)
Dept. of Building Inspection
Approved April 15, 2026. Reviewer: Diaz Jonathan.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved January 23, 2026. Reviewer: Mautner Allegra.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved January 13, 2026. Reviewer: Arriola Laura.
Planning (CP-ZOC)
SF Planning Department
Approved January 07, 2026. Reviewer: Vimr Jonathan.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 06, 2026. Reviewer: Dennis Rassendyll.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved May 04, 2026. Reviewer: Hoang Tina.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 09, 2026. Reviewer: Luu Sarah.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved December 29, 2025. Reviewer: Chan Thomas.
Post-Issuance Addenda
Addendum #1In Review
0 of 2 stations approved· last activity 2026-08
Addendum #2In Review
0 of 2 stations approved· last activity 2026-08
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.