Estimated Timeline
Permit issued — plan check completeJune 26, 2026
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2025
Permit Filed
New construction permit filed with DBI
Jun 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 1 mo
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 05, 2026. Reviewer: Mautner Allegra.
Building Code (BLDG)
Dept. of Building Inspection
Approved May 28, 2026. Reviewer: Diaz Jonathan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 12, 2026. Reviewer: Imson Grace.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 12, 2026. Reviewer: Dennis Rassendyll.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Louie Timothy.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 15, 2026. Reviewer: Blackshear John.
Post-Issuance Addenda
Addendum #1In Review
3 of 7 stations approved· last activity 2026-08
Addendum #2In Review
0 of 2 stations approved· last activity 2026-08
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.