Estimated Timeline
4 of 7 stations approved57% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on March 26, 2026. 1 round(s) of review. Reviewer: Diaz Jonathan.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on March 19, 2026. 1 round(s) of review. Reviewer: Bryan Ong.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 12, 2026. Reviewer: Imson Grace.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 12, 2026. Reviewer: Dennis Rassendyll.
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Louie Timothy.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved February 10, 2026. Reviewer: Casey Ryan.
Bottleneck Watch: Building Code
Building Code currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
Dec 2025
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2025
Permit Filed
New construction permit filed with DBI
Sep 2026 – Apr 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.