Estimated Timeline
0 of 7 stations approved0% complete
Key Milestones
Jul 2026
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2026
Permit Filed
New construction permit filed with DBI
Jan 2027 – Oct 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Horn Jeffrey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street is the longest-running active review station on this project.