San Francisco / Excelsior / 548 Carter St

548 Carter St

21-unit 3-story residential project erect a 3 story 21 dwelling unit

Permit Issued — Under Construction21 UnitsStandard Entitlement
Permit Filed
Aug 2002
Active Review Since
Aug 2002
Review Stations
0 of 4
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

April 2003

Permit issued on April 22, 2003. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 4 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Tam Tina.
In Review
Plan Approval Mech. (PAD-MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Hu Tiecheng.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Gravanis Jim.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Omokaro Eric.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Aug 2002
Permit Filed
New construction permit filed with DBI
Aug 2002
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2003
Permit Issued
Construction can begin
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.