Estimated Timeline
0 of 8 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Fu Ben.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Valle Jaime.
Central Engineering (CNT-CE)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date.
Central Plan Check (CNT-PC)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Miniano Danny.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Hayes Janice.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Aug 2004
Permit Filed
New construction permit filed with DBI
Aug 2004
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2013
Permit Issued
Construction can begin
May 2015
Construction Complete
Certificate of occupancy issued