Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Crawford Rick.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Pada Rodolfo.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Stumpp Fred.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 2 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Sep 2005
Permit Filed
New construction permit filed with DBI
Sep 2005
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2012
Permit Issued
Construction can begin
Feb 2014
Construction Complete
Certificate of occupancy issued