Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Fu Ben.
Plan Approval Mech. (PAD-MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zhan James.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Stephenson Tod.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gaime Berhane.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2005
Permit Filed
New construction permit filed with DBI
Dec 2005
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2007
Permit Issued
Construction can begin