Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Young Sharon.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Vellve Sara.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Yu Cyril.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Micki Jones.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2007
Permit Filed
New construction permit filed with DBI
Dec 2007
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2016
Permit Issued
Construction can begin
Aug 2018
Construction Complete
Certificate of occupancy issued