Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Chun Robert.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: O'Keeffe Tracy.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Lau H Grace.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Jun 2008
Permit Filed
New construction permit filed with DBI
Jun 2008
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2015
Permit Issued
Construction can begin
Feb 2019
Construction Complete
Certificate of occupancy issued