Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Mosquera Gonzalo.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Huang Vivian.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Curd John.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Mosquera Gonzalo.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 2 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2009
Permit Filed
New construction permit filed with DBI
Dec 2009
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2015
Permit Issued
Construction can begin
Jul 2016
Construction Complete
Certificate of occupancy issued