San Francisco / Bayview Hunters Point / 401 Innes Av

401 Innes Av

35-unit 5-story residential project to erect 5 story, 35 residential units with parking

Construction Complete35 UnitsAB 2011 Ministerial$9.1M Est. Cost
Permit Filed
Dec 2009
Active Review Since
Dec 2009
Review Stations
0 of 6
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

April 2013

Permit issued on April 16, 2013. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 6 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ho Gary.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Miniano Danny.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lau Danny.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Key Milestones
Dec 2009
Permit Filed
New construction permit filed with DBI
Dec 2009
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2013
Permit Issued
Construction can begin
Apr 2017
Construction Complete
Certificate of occupancy issued
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.