Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Zee Howard.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Debella Al.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Oct 2010
Permit Filed
New construction permit filed with DBI
Oct 2010
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2015
Permit Issued
Construction can begin
Feb 2021
Construction Complete
Certificate of occupancy issued