Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Pang David.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Sucre Richard.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Sucre Richard.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Hayes Janice.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Dec 2010
Permit Filed
New construction permit filed with DBI
Dec 2010
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2013
Permit Issued
Construction can begin
Mar 2017
Construction Complete
Certificate of occupancy issued