Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Cabreros Glenn.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Cheung Jimmy.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Debella Al.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Johnson Carla.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Apr 2012
Permit Filed
New construction permit filed with DBI
Apr 2012
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2014
Permit Issued
Construction can begin
Feb 2018
Construction Complete
Certificate of occupancy issued