Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Wong Irene.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Miniano Danny.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Curd John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Jul 2012
Permit Filed
New construction permit filed with DBI
Jul 2012
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2013
Permit Issued
Construction can begin
Dec 2015
Construction Complete
Certificate of occupancy issued