Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Guy Kevin.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Hu Qi.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Hayes Janice.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Levin Pamela.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Oct 2012
Permit Filed
New construction permit filed with DBI
Oct 2012
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2013
Permit Issued
Construction can begin
Mar 2017
Construction Complete
Certificate of occupancy issued