Estimated Timeline
0 of 4 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yau Willy Hoi-C.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Hayes Janice.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gaime Berhane.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Apr 2013
Permit Filed
New construction permit filed with DBI
Apr 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2013
Permit Issued
Construction can begin
Feb 2017
Construction Complete
Certificate of occupancy issued