Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Vu Doug.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Hayes Janice.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 4 cycle(s) to date. Reviewer: Pang David.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Jun 2013
Permit Filed
New construction permit filed with DBI
Jun 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2017
Permit Issued
Construction can begin
Nov 2025
Construction Complete
Certificate of occupancy issued