Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Conner Kate.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Liu Chu.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lai Jeff.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Stumpp Fred.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Jul 2013
Permit Filed
New construction permit filed with DBI
Jul 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2014
Permit Issued
Construction can begin
Jun 2016
Construction Complete
Certificate of occupancy issued