Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Snyder Mathew.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Curd John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Jeung Martita.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Jimmy.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Aug 2013
Permit Filed
New construction permit filed with DBI
Aug 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2014
Permit Issued
Construction can begin
Jun 2017
Construction Complete
Certificate of occupancy issued