San Francisco / Bayview Hunters Point / 140 Middle Point Rd

140 Middle Point Rd

50-unit 5-story residential project erect 5-story, type 3, 1 basement/garage, 50 dwelling units building.

Construction Complete50 UnitsStandard Entitlement$11.1M Est. Cost
Permit Filed
Aug 2013
Active Review Since
Aug 2013
Review Stations
0 of 6
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

November 2014

Permit issued on November 03, 2014. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Snyder Mathew.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Curd John.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Jeung Martita.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Cheung Jimmy.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Aug 2013
Permit Filed
New construction permit filed with DBI
Aug 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2014
Permit Issued
Construction can begin
Jun 2017
Construction Complete
Certificate of occupancy issued
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.