Estimated Timeline
0 of 4 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yin Diane.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gaime Berhane.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Bowden Attica.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Sep 2013
Permit Filed
New construction permit filed with DBI
Sep 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2014
Permit Issued
Construction can begin
Oct 2018
Construction Complete
Certificate of occupancy issued