Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Speirs Jeffrey.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Balmy Alec.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Chan Joseph.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Gaime Berhane.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Oct 2013
Permit Filed
New construction permit filed with DBI
Oct 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2014
Permit Issued
Construction can begin
Nov 2016
Construction Complete
Certificate of occupancy issued