Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Wong Irene.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Micki Jones.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Cy Liongtian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Brownell Amy.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Dec 2013
Permit Filed
New construction permit filed with DBI
Dec 2013
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2014
Permit Issued
Construction can begin
Jul 2016
Construction Complete
Certificate of occupancy issued