Estimated Timeline
0 of 4 stations approved0% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yau Willy Hoi-C.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Ng Roger.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 6 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Jan 2015
Permit Filed
New construction permit filed with DBI
Jan 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2015
Permit Issued
Construction can begin
Aug 2019
Construction Complete
Certificate of occupancy issued