Estimated Timeline
0 of 7 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Vu Doug.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Howard Brett.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Hayes Janice.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Walls Mark.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Szu-Whitney Monica.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Cy Liongtian.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Luu Sarah.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Jul 2015
Permit Filed
New construction permit filed with DBI
Jul 2015
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2016
Permit Issued
Construction can begin
Mar 2018
Construction Complete
Certificate of occupancy issued