Estimated Timeline
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Woods Mary.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Eng Amy.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Kreuscher Daniel.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Oct 2015
Permit Filed
New construction permit filed with DBI
Oct 2015
Electronic Plan Review Activated
Plans distributed to all review stations
May 2018
Permit Issued
Construction can begin
Apr 2022
Construction Complete